PMP Exam Set E – Q45

A project manager is using a Risk Diagramming technique that is a graphical representation of situations showing causal influences, time ordering of events and other relationships among variables and outcomes. This would be:

A. A System flow chart
B. An Influence Diagram
C. Pareto chart
D. Risk flow diagram

B. An Influence Diagram