PMP Exam Set F – Q21

When would Rolling Wave Planning be useful in a project?

A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.
B. You should use Rolling Wave Planning to determine the correct sequencing for long term items.
C. You should use Rolling Wave Planning to help you organize team member’s activities within a large project group.
D. You should use Rolling Wave Planning to help you determine which activities are more important and should be done first.

A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.