PMP Exam Set F – Q21

When would Rolling Wave Planning be useful in a project?

A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.
B. You should use Rolling Wave Planning to determine the correct sequencing for long term items.
C. You should use Rolling Wave Planning to help you organize team member’s activities within a large project group.
D. You should use Rolling Wave Planning to help you determine which activities are more important and should be done first.

A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.

PMP Exam Set B – Q19

Due to the unexpected release of a similar product from a competitor, the Widgets International executive team has stepped up the pressure on the product team to release the Widget product 3 months earlier. The project manager uses what technique to shorten the schedule but maintain the project scope?

A. Schedule compression
B. Rolling wave planning
C. Schedule network analysis
D. Schedule management planning

A. Schedule compression