PMP Exam Set B – Q70

Peter, a project manager, is updating the status of his project. Based on the performance indices, he expects the project to finish a month earlier than the planned finish date. However, he expects the project to exceed the budgeted costs. What can you say about the schedule performance index (SPI) of the project?

A. The SPI is less than 1.0.
B. The SPI equals the CPI.
C. The SPI is greater than 1.0.
D. The SPI is equal to 1.0.

C. The SPI is greater than 1.0.