PMP Exam Set A – Q11

Bill is the project manager of a software project that is originally estimated to complete in 12 months. 2 months into the project, it is discovered that the original estimating assumptions were fundamentally flawed. The Estimate at Completion (EAC) in such a project will be:

A. EAC = AC + Bottom-up ETC
B. EAC = BAC/CPI
C. EAC = AC + [BAC – EV]/CPI
D. EAC = AC + BAC – EV

A. EAC = AC + Bottom-up ETC