During a weekly status meeting a team member suggests adding a component to the project. As the project manager, you indicate that all focus should be put on the current scope and don’t worry about any enhancements. Focusing on the current scope is an example of?
A. Gold plating
B. Scope verification
C. Scope management
D. Change control