You are managing a project to design microprocessor control systems. The design work was estimated to complete in 3.5 months, with seven milestones. The sixth milestone is the prototype to be handed over to manufacturing. All milestones before prototyping have been completed ahead of schedule with 6th one being delayed for 4 months as the prototype has been sent back several times, due to conflicts between departments. You are now planning to hold a meeting to review the design specifications, and handle conflicts between design and manufacturing. Who is at fault?
A. The scheduler.
B. The project manager.
C. The manufacturer.
D. The design engineer.