PMP Exam Set A – Q52

A software vendor on your project is hoping to be awarded a contract providing software for another project at your company. You are not the manager of the other project. However, the vendor offers you tickets to an upcoming professional sports event if you will “put in a good word” for his company to vendor selection team of the other project. What do you do?

A. Fire the vendor.
B. Decline the tickets, but provide a recommendation for the vendor.
C. Decline the tickets and notify appropriate management of the situation.
D. Accept the tickets if company policy allows it, and provide a recommendation for that vendor to the other project team.

C. Decline the tickets and notify appropriate management of the situation.