PMP Exam Set A – Q53

Terry is managing a healthcare software development project using state-of-the-art technology. Stakeholder management is very crucial for the success of this project. The stakeholder involvement and influence is significant on this project. During which of following project stages, stakeholder management will be the most challenging task for Terry?

A. Early during the project execution
B. Towards the end of the project execution
C. Towards the closure of the project
D. Halfway through the project execution

A. Early during the project execution