PMP Exam Set A – Q60

John has just been assigned as the project manager of a project to develop a complex product. The project is in the Define Scope phase. Which of these tools / techniques will not be used by John in this phase?

A. Lateral thinking
B. Process analysis
C. Product breakdown
D. Value engineering

B. Process analysis