PMP Exam Set A – Q94

A project manager determines that there are 15 communication channels in the project. The number of stakeholders in the project must then be:

A. 15 stakeholders
B. 6 stakeholders
C. 8 stakeholders
D. 105 stakeholders

B. 6 stakeholders