PMP Exam Set D – Q68

There are 10 stakeholders in MegaMart’s ERP deployment project. How many potential communications channels are there?

A. 25
B. 10
C. 45
D. 30

C. 45

PMP Exam Set A – Q94

A project manager determines that there are 15 communication channels in the project. The number of stakeholders in the project must then be:

A. 15 stakeholders
B. 6 stakeholders
C. 8 stakeholders
D. 105 stakeholders

B. 6 stakeholders