PMP Exam Set B – Q59

Alex is managing a hotel refurbishment project. He has identified his project’s key stakeholders. Alex now wants to expand this list of stakeholders and convert it to a comprehensive list of project stakeholders. What should Alex do?

A. Do not spend more time on identifying the non-key stakeholders
B. Seek expert judgment from the identified key stakeholders
C. Request the project sponsor to provide the details of the remaining stakeholders
D. Carry out a stakeholder analysis with the identified key stakeholders

B. Seek expert judgment from the identified key stakeholders