PMP Exam Set B – Q60

A project manager colleague of yours is currently working under contract on a short term project. He has expressed some concerns about finding work after the project ends. The project he is working on is currently ahead of schedule and he expects they will finish a month sooner than initially expected. What advice would be appropriate to provide him?

A. Slow down work on the project to have it finish on schedule.
B. Continue the work within the project’s scope and possibly finish ahead of schedule.
C. Exaggerate his experience to the sponsor to try to get a project manager position for him on other upcoming projects.
D. Inform the client the project is behind schedule and it will have to be extended.

B. Continue the work within the project’s scope and possibly finish ahead of schedule.