PMP Exam Set B – Q85

You are working as a project manager for a high yield crop development project. Data from the weather agency shows an unfavorable weather pattern for next few months. As a senior project manager, you want to assess the feasibility of the schedule under adverse conditions and provide some insights to your team. This way, your team can prepare some reserves and plan risk responses if unfavorable conditions exist during execution. Which of the following techniques should you use to assess the feasibility of the schedule?

A. Pareto charts
B. Variance analysis
C. Crashing
D. Monte Carlo analysis

D. Monte Carlo analysis