PMP Exam Set B – Q86

The project manager of a large construction project is responsible for ensuring that all changes to the building plans are approved and tracked before they are implemented. These activities form part of which process?

A. Manage Scope
B. Perform Configuration Management
C. Perform Integrated change control
D. Perform Quality Control

C. Perform Integrated change control