Emily has recently been asked to manage the deployment of an enterprise resource planning system for her organization. Emily has sent her project sponsor a meeting request to discuss her project’s stakeholder management plan. The sponsor believes that the stakeholder management planning is not relevant for such internal projects. The sponsor believes that only the scope, schedule and cost management plans are sufficient for such projects. The sponsor has asked Emily to describe the objective of the meeting. Which of the following is the best response to this question?
A. The objective of the meeting is to develop the project stakeholder register.
B. The objective of the meeting is to develop strategies to effectively keep the project stakeholder engaged and committed to the project.
C. The objective of the meeting is to conform to the PMBOK standards.
D. The objective of the meeting is to identify and classify project stakeholders.