PMP Exam Set C – Q1

A project manager presented Earned value analysis data in a tabular format while providing a performance report. An alternative way in which the project manager could have presented the Earned value analysis data is by using:

A. A linear graph
B. An S-curve
C. A logarithmic curve
D. An Epsilon graph

B. An S-curve