You took over a project from an individual who was let go. You are reading the project documentation and found the project charter was signed by five managers. What should be your primary concern at this time?
A. Determining reporting structure
B. Communicating in a matrix organization
C. Getting a single sponsor
D. Identifying who can represent the project for change control