You are a Project Manager for a company that has a composite organization structure. The current project you are managing is coming to an end. There are a number of activities that need to be completed including releasing project resources. All of the following statements are examples or true statements related to releasing project resources in this company EXCEPT?
A. Documenting the release date for project resources in the project management plan
B. Transferring project equipment to the regular operations of the company
C. Reassigning project team members to a new project within the company
D. Transferring the documented lessons learned into the lessons learned database