PMP Exam Set C – Q49

Johan is a project manager working for a Norwegian accounting firm. To get results, Johan often tells team members that if deadlines are not met, he will have to discuss their performance with their functional managers. Johan’s organization can not be a:

A. Projectized organization
B. Weak matrix organization
C. Functional organization
D. Strong matrix organization

A. Projectized organization