PMP Exam Set C – Q48

Costs incurred in one area of a project can offset costs in another area of the same project. However, it is not the best practice to consider only the costs of project execution when making project decisions. What must also be considered?

A. Costs of non-conformance
B. Planning costs
C. Operating costs
D. Initiating costs

C. Operating costs