PMP Exam Set C – Q60

A company you worked for several years ago is bidding on a project your new company will be starting in approximately 6 months. You have been selected to manage the project, and will be participating in the vendor selection processes. What should you do?

A. Notify the stakeholders of your status and excuse yourself from the vendor selection process.
B. Provide the vendor selection committee with as much detail as you can remember about your former company so that the best decision can be reached.
C. Notify the project stakeholders of your status as a former employee of the bidding company, and comply with their preferences for how you participate in the vendor selection process.
D. Do nothing.

C. Notify the project stakeholders of your status as a former employee of the bidding company, and comply with their preferences for how you participate in the vendor selection process.