A project manager is informed that a limited number of resources are going to be available for his project. He creates a project schedule by adding buffers to the project to protect the target finish date. What type of schedule network analysis is he using?
A. What-if analysis
B. Critical path method
C. Critical chain method
D. Resource leveling.