Peter is the project manager of an external project for a customer. The project is expected to take about a year to complete. Six months into the project, the customer informs Peter that the project needs to be scrapped. During which of the following processes would procedures be developed to handle early termination of a project?
A. Develop Project Charter
B. Close Project or Phase
C. Define Scope
D. Control Procurements