At division project status meeting, a dashboard of cost metrics for each project is distributed to all attendees, and each project manager is presenting the status of their project. The metrics for one project show a BAC of $1100, an EV of $998, and a EAC of $1099. However the project manager is reporting an ETC of $354 in her presentation. What do you do?
A. Notify the appropriate management there is a calculation error.
B. Nothing.
C. Advise the project manager to take the additional funds from her project contingency budget.
D. Congratulate the project manager for being under budget.