PMP Exam Set D – Q94

At division project status meeting, a dashboard of cost metrics for each project is distributed to all attendees, and each project manager is presenting the status of their project. The metrics for one project show a BAC of $1100, an EV of $998, and a EAC of $1099. However the project manager is reporting an ETC of $354 in her presentation. What do you do?

A. Notify the appropriate management there is a calculation error.
B. Nothing.
C. Advise the project manager to take the additional funds from her project contingency budget.
D. Congratulate the project manager for being under budget.

A. Notify the appropriate management there is a calculation error.