PMP Exam Set E – Q26

The Executive VP of Finance has informed you that you will be the Project Manager for an energy audit the company is performing in order to save expenses. He has tasked you to identify the stakeholders and to start documenting the high-level assumptions and constraints. Your project is in what stage?

A. Initiating
B. Planning
C. Monitoring & Controlling
D. Executing

A. Initiating