You have completed your estimates for your project and determined that it will take 10 months to complete. However, your project sponsor insists that it be completed in 9 months. How do you handle this?
A. Increase the budget by 10%
B. Inform the sponsor you will have to explore the options before committing to that timeline.
C. Reduce scope
D. Add resources