PMP Exam Set E – Q95 ( PMBOK 6th edition )

You are an experienced project manager and have managed several data center migration projects. You are currently conducting training on the databases, spreadsheets and management plans you will be using during the lifecycle of the project. This training is a tool and technique in what process?

A. Manage Team
B. Acquire Resources
C. Develop Team
D. Control Quality

C. Develop Team