During the Control Scope phase, analysis of the scope performance resulted in a change request to the scope baseline. This change request will be processed for review and disposition in the:

A. Control Quality phase
B. Perform Integrated Change Control phase
C. Monitor and Control Project Work phase
D. Validate Scope phase

B. Perform Integrated Change Control phase