You are working with your customers on completed deliverables in your electronic parts manufacturing project. Since these parts are exported to other countries, they need more testing before your customers accept them. In this scenario, which of the following statements about the completed deliverables is CORRECT?
A. Completed deliverables not accepted by customers must be forwarded to the close project or phase process
B. Deliverables formally accepted by customers must be moved to organizational process assets
C. Deliverables formally accepted by customers are forwarded to the validate scope process
D. Completed deliverables not accepted by customers must require a change request for defect repair