A project manager creates a component-specific tool to verify that a set of required steps have been performed. This tool is called a:
A. Risk Register
B. Assumptions log
C. Checklist
D. Plan-Do-Act-Check
A project manager creates a component-specific tool to verify that a set of required steps have been performed. This tool is called a:
A. Risk Register
B. Assumptions log
C. Checklist
D. Plan-Do-Act-Check