As the project manager of a large project, you have just completed the Estimate Costs process. As you begin the Determine Budget process, which of the following would you require as inputs?
A. Activity cost estimates, Basis of estimates
B. Activity cost estimates, Activity resource estimates
C. Resource breakdown structure, Agreements
D. Activity cost estimates, Staff management plan