The project charter defines the overall scope and objectives of a project. Considering different inputs to the project charter, which of the following is NOT a correct statement?
A. Government or industry standards cannot be used as an input to develop a project charter
B. The project’s business case is an input to the Develop Project Charter process
C. Organizational process assets are input to the Develop Project Charter process
D. When projects are executed for external customers, a contract or an agreement is used as an input to the charter