PMP Exam Set G – Q13 ( PMBOK 6th edition )

The Project Manager controls the interfacing and overlapping areas of the organization’s procurement processes, and the project schedule with processes from this area:

A. Project Resource Management
B. Project Scope Management
C. Project Risk Management
D. Project Integration Management

D. Project Integration Management