PMP Exam Set G – Q19

Why are the approved change requests input to the Direct and Manage Project Work process?

A. Approved change requests may be rejected by the project team during the Direct and Manage Project Work process.
B. Approved change requests are implemented by the project team during the Direct and Manage Project Work process.
C. Approved change requests are sent to the Change Control Board during the Direct and Manage Project Work process.
D. Approved change requests are reviewed by the project team during the Direct and Manage Project Work process.

B. Approved change requests are implemented by the project team during the Direct and Manage Project Work process.