PMP Exam Set G – Q24

You are working in an Information Technology project as a project manager to develop a shopping website for your customers. Some key stakeholders in the project suggested scope changes to improve the look and feel of the website. Your team has analyzed the impact of these changes and presented to the change control board for approval. What should be your next step if the change control board accepts all proposed changes?

A. Implement the change request and update stakeholders
B. Review change control board decisions and inform stakeholders for their input
C. Conduct a team status meeting to update the progress on change requests
D. Revise cost estimates, schedule dates, resource requirements and planning documents

D. Revise cost estimates, schedule dates, resource requirements and planning documents