PMP Exam Set G – Q25

A project manager was assigned to a project as the project charter was being developed. Which of the following is an input that the project manager will utilize to develop the project charter?

A. Make-or-Buy analysis
B. Organizational Process Assets
C. Project Acceptance Criteria
D. Project Scope Statement

B. Organizational Process Assets