PMP Exam Set G – Q36 ( PMBOK 6th edition )

A project manager is currently ensuring that the stakeholders clearly understand the project goals, objectives, benefits and risks. This relates to which of the following processes?

A. Monitor Stakeholder Engagement
B. Identify Stakeholders
C. Plan Communications Management
D. Manage Stakeholder Engagement

D. Manage Stakeholder Engagement