PMP Exam Set G – Q36 ( PMBOK 6th edition )

A project manager is currently ensuring that the stakeholders clearly understand the project goals, objectives, benefits and risks. This relates to which of the following processes?

A. Monitor Stakeholder Engagement
B. Identify Stakeholders
C. Plan Communications Management
D. Manage Stakeholder Engagement

D. Manage Stakeholder Engagement

PMP Exam Set E – Q68 ( PMBOK 6th edition )

Which of the following is the process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement?

A. Manage Stakeholder Engagement
B. Monitor Stakeholder Engagement
C. Manage Communications
D. Monitor Communications

A. Manage Stakeholder Engagement