PMP Exam Set G – Q57

Your manager is presenting a status report of all projects being run in his division. He reports that all projects are showing a positive CV. However, you know that your status reports for the last several weeks have been reporting a negative CV. What do you do?

A. Do nothing.
B. Offer to review all your manager’s combined status reports before he presents them.
C. Notify the appropriate management immediately.
D. Ask your manager if that information was simply a typographical error.

C. Notify the appropriate management immediately.