PMP Exam Set G – Q56

As part of a strategy to handle negative risk, a project manager decided to adopt less complex processes, conduct more tests and choose a more stable supplier. What strategy would this be classified as?

A. Acceptance
B. Transference
C. Mitigation
D. Avoidance

C. Mitigation