PMP Exam Set G – Q60

Most project management software packages use a method of constructing a project schedule network diagram known as:

A. Activity Diagramming Method
B. Precedence Diagramming Method
C. Project Diagramming Method
D. Critical Diagramming Method

B. Precedence Diagramming Method
Tagged with 
Activity Diagramming Method Critical Diagramming Method Precedence Diagramming Method Project Diagramming Method project schedule network diagram
 

Post navigation

Previous Post« Previous PMP Exam Set G – Q59
Next Post PMP Exam Set G – Q61Next »
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2023 Premium PMP Exam Questions
×Close