PMP Exam Set G – Q61

Breaking down project activities into smaller components in order to obtain a more accurate cost estimate is called:

A. Work breakdown structure
B. Analogous estimating
C. Decomposition
D. Bottom-up estimating

D. Bottom-up estimating