PMP Exam Set E – Q68 ( PMBOK 6th edition )

Which of the following is the process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement?

A. Manage Stakeholder Engagement
B. Monitor Stakeholder Engagement
C. Manage Communications
D. Monitor Communications

A. Manage Stakeholder Engagement