PMP Exam Set E – Q48

Sensitivity analysis helps to determine which risks have the most potential impact on the project. A project manager prepared a display chart of sensitivity analysis for his project. The diagram contained a series of bars with the length of the bars corresponding to the risk impact on the project. The longer the bars, the greater was the risk presented. Such a diagram is likely to be:

A. An assessment diagram
B. A triangular distribution
C. A tornado diagram
D. A funnel distribution

C. A tornado diagram

PMP Exam Set C – Q44

You are analyzing the risk in a project and decide to do sensitivity analysis to determine which risks have the most potential impact on the project. You look at a tool to help compare the relative importance of variables that have a high degree of uncertainty to those that are more stable. One such tool is:

A. Beta Distribution
B. Multicriteria decision analysis
C. Control Chart
D. Tornado Diagram

D. Tornado Diagram