A seller organization was executing work for a project under a contract. During the course of the project, a number of disputes arose over the scope and quality of work. Which of the following is the preferred method of resolving these claims?
A. Alternative dispute resolution (ADR)
B. Claims court
C. Appeals court
D. Negotiation