PMP Exam Set A – Q30

A key project in an organization has been ignored due to high travel expenses associated with the movement of subject matter experts and other specialists across various project locations. Which of the following will permit such a project to be taken up in a cost-efficient manner?

A. Management sign-off
B. Negotiation
C. Virtual teams
D. Co-location

C. Virtual teams

PMP Exam Set A – Q26

A seller organization was executing work for a project under a contract. During the course of the project, a number of disputes arose over the scope and quality of work. Which of the following is the preferred method of resolving these claims?

A. Alternative dispute resolution (ADR)
B. Claims court
C. Appeals court
D. Negotiation

D. Negotiation