In a multi-phase project, the procurement team decided to close the procurements applicable to a particular phase of the project. What happens to unresolved claims?
A. Unresolved claims are usually resolved at the end of all phases of the project.
B. Unresolved claims are also closed when the procurements for that phase are closed.
C. Unresolved claims remain open for a period of 1 year from closure of procurements.
D. Unresolved claims may still be subject to litigation after closure.